Name Of Project

PROVISION OF A HIGH VOLTAGE SHORE CONNECTION (HVSC) SYSTEM USING ENERGY EFFICIENT EQUIPMENT, IN THE PORT OF VALLETTA, GRAND HARBOUR

MALTA

The project allows cruise liners and cargo ships to switch off their gasoil- or heavy-fuel-oil-fired engines and plug in to shoreside electricity to energise their onboard systems while they are berthed in port. 

Scope of Project

-Construction of the buildings for the Frequency Converter Station ( FCS 1 and FCS 3)

-33kV supplies from Marsa North DC to the FCS1 and FCS3 buildings

-Installation of two lengths of 33kV submarine cables and communication/fibre optic cables

-Supply and installation of all the 11 kV cables

-Supply and installation of a 100 mm heavy duty PVC duct, a communication cable  and a fibre optic cable (inside a 50mm HDPE duct)

-The construction of a significantly long culvert and duct bank

-High level steel support structure

-The provision of LV/ELV systems

-Restoration of Historical building ( including   facade stone, apertures, steel structure,  internal walls, roof covering )

-The provision of asphalt works

-Operating the HVSC system at the five quays for a period of two years

-Design, supply, installation, testing and commissioning of the following equipment

  • 33kV gas insulated incoming switchboards.
  • The 33kV, 24 pulse input rectifier transformers
  • The auxiliaries’ supply transformers
  • The SFCs complete with their cooling equipment
  • The rectifier output transformers
  • The rectifier transformers output 11 kV gas insulated switchgear
  • The 11kV RLC filters’ switchgear
  • The galvanic isolation transformers’ neutral earthing resistors with related switchgear
  • The 11 /6.6kV galvanic isolation transformers and their related pre-magnetisation transformers and voltage regulation equipment.
  • The on-shore ship connector boxes
  • The Shore-to-ship mobile cable management equipment
  • 8 passenger lift
  • Automatic start standby generator
  • 1 OV DC system batteries

Main Contractor:  Excel Sis

CLIENT:
Infrasturcture Malta
project type:
Infrastructure
LOCATION:
Valetta, Malta
SCOPE:
Shore Connection, Construction and Restoration Works
Status:
On-going
dURATION:
30 Months
(2020-2023)